Retrofitting
MJTs onto combustion gas turbine. Industrial combustion
gas turbines are well known for being especially hard to bolt
and unbolt. No only are the bolts and nuts very large, they are
not forgiving and will leak when not preloaded properly since
the flanges are metal-to-metal with no gaskets. The problem can
be exacerbated when the bolts are in a hard-to-access area or
lack heating holes for thermal tightening.
One particular
unit in a refinery suffered from all of these problems with a large
number of its bolts. Some bolts literally took hours to bolt and
unbolt, especially when they had not been opened in a long time.
Sometimes bolts could not be freed and would have to be cut with
a torch to be removed. In addition, the unit was notorious for
developing hot air leaks after being overhauled and, consequently,
would have to be shut down for bolt retightening. Even then the
leak would not completely disappear, since the casing faces were
distorted due to previous leaks.
All
of these problems made this unit a very good candidate to replace
the original turbine bolting with MJTs. The first step was to decide
which bolts to replace with MJTs during the next unit overhaul.
The unit had many bolts and it would have been uneconomical to
replace them all. Instead, efforts were concentrated on selecting
a few large-diameter bolts in inaccessible and critical areas to
be replaced. Fig. 4 shows a cross-section of the gas turbine casing,
with arrows pointing to the bolts that were selected to be changed.
As can be seen from Fig. 5, these bolts are situated at the corners
of the casings and are among the largest in diameter (2 in.). Furthermore,
the original bolts had a large hexagonal socket cap, which meant
that a special socket had to be used to torque them. It was felt
that replacing these bolts would not only take care of the most
problematic bolts in the area but would also have the most positive
effect on reducing leaks.
Once
it was decided which bolts would be retrofitted with MJTs, a custom
design was developed with help from the manufacturer. The bolt
would have to fit in the recessed area intended for the original
bolt. It would also have to allow enough clearance above it to
access the jacking bolts. Since detailed drawings for the bolts
and the casing were not available, detailed measurements of some
spare bolts along with the casing had to be taken. Once these details
were collected, they were sent to the manufacturer. It came up
with a design similar to what is shown in Fig. 6.
The next step
was to come up with an appropriate material for this application,
taking into account both the designed preload of the bolting and
the temperature that the bolts will have to withstand. After some
background search as well as consultation with different turbine
manufacturers, a preload close to the original design was selected
that would help in minimizing the leak problem. Actual casing operating
temperature was measured by taking a thermal image of the unit
when it was running (Fig. 7). Consequently, an estimate of the
maximum temperatures the bolting will be exposed to over its life
was determined. Samples of the original bolting material were analyzed
to try to guess its composition and the design constraints of the
original bolting designer. A final selection of bolting materials
was reached with help from the MJT manufacturer as well as in-house
company engineering expertise. Finally, the designed bolts were
manufactured and installed in a major unit overhaul.
MJT
Assessment. We found that they were more expensive than
the original OEM bolts (about 40% more in this particular application).
In addition, most machinists do not know how to properly install
MJTs, so some time has to be spent explaining the proper installation
sequence. Having said this, we feel that MJTs have performed
very well in our particular application. time required to install
bolts has shrunk from about 30-60 min. to less than 5 min. per
bolt. Moreover, all the problems that we were facing with the
original bolts have now disappeared. No heavy hammering or heating
with torches is required to set these bolts. In our application,
the required torque has decreased from the original 3,313 ft
lb to 65 ft lb (an advantage of more than 50:1). This new torque
can be easily and accurately applied by hand. This is achieved
with confidence that the bolts were tightened to the target preload.
As has been mentioned
earlier, this turbine had a long history of developing leaks in
its horizontal and vertical flanges. In the past, the leaks were
so severe tha tthey have caused unevenness in the turbine casing
(Fig. 8). After MJTs were installed and the unit was run, some
clear leaks did develop but only in the areas where the new bolts
were not installed on the casing. This shows that these bolts are
as good ormost likely better than the original bolts in applying
the proper preload and preventing hot air leaks on the casing.
The
decision to use MJTs should not be automatic; each bolting problem
should be evaluated separately to decide if they can be used and
are worth the engineering effort to retrofit them to solve the
problem. Other bolting methods are very useful and effective in
many applications. In our opinion, however, MJTs should at least
be considered for large or especially critical bolting applications
to improve safety and reliability. They should be considered for
new installations that require large bolts or high torquing values
and preloads.
ACKNOWLEDGMENTS
Many thanks go
to a number of engineers working in various departments of Saudi
Aramco for suggesting and supporting this project, particularly
A. R. Al-Khowaiter from Aramco and the engineering staff at Superbolt
Inc.
BIBLIOGRAPHY
Steinbock, R., "Multi-Bolt
Mechanical Tensioners," ASME PVP - Vol. 158, Advances in Bolted
Joint Technology, 1989.
Dekker, M., An
introduction to the design and behavior of bolted joints, New York,
1981. |