Power Examples: Press Examples: Compressor Examples: Hydro Examples: Mining Examples: Petrochemical Examples: Steel Mill Examples: Various:
|
|
Leveltek Leveler
Leveltek began receiving end user demand for a more powerful leveler. This resulted in a larger machine design that required an extremely high preload to bolt the frame together. Each 4” diameter stud would require 750,000 lb preload, and standard hex nuts would require approximately 44,000 ft-lb torque to achieve the given preload. Superbolt® provided the bolting solution and manufactured multi-jackbolt tensioners, flexnuts, and studs. These components hold the entire frame together.
Two workers installed the Superbolt® tensioners in just one hour. They were able to work safely with 1/2” drive air impacts and 1/2” drive hand torque wrenches. Only 120 ft-lb jackbolt torque was required to achieve the 750,000 lb preload.
|